We have recently started construction of a new roundabout on the A5 Watling Street between M6 J12 and A449/A5 Gailey Roundabout. The new roundabout will provide access to the development once it’s complete. The works will be delivered in phases, with completion expected in early 2027.
Narrow lanes on the eastbound and westbound carriageways. These narrow lanes are required to safely facilitate the construction of the new eastbound footway/cycleway and the roundabout, and will remain in place for the duration of the works. A temporary 30mph speed limit will also be in place.
Please note, right turns will not be permitted from properties within the working area.
Other traffic management required for the roundabout construction will include some full road closures. These are expected to take place later in the programme, and we will provide further details well in advance of these works.